Welcome to the Co-op
Welcome to the co-op, from your friendly team of member service representatives! Assistance is provided by Paulding Putnam for those moving into the service territory who need to start electric service, as well as for those who need existing electric service discontinued or upgraded.
New Member Handbook & ResourcesStop Electric Service
To disconnect electric service, current members must contact the Paulding Putnam office at (800) 686-2357.
Need help with a service limiter? Visit our Service Limiters page.
How To Apply for Membership & Start Electric Service
Need electric service at a home in Paulding Putnam’s service territory? Contact our office to get started, (800) 866-2357 or click the Service Sign Up button below.
You do not need to complete the application before contacting us. Our friendly staff will walk you through the process and answer any questions.
- Office hours: Monday to Friday, 7 a.m. to 3:30 p.m.
- Office location: 401 McDonald Pike, Paulding, Ohio
Please note:
- Documentation at Paulding Putnam is maintained only in electronic format
By applying for and receiving electric service from Paulding Putnam the applicant becomes a member of the cooperative. Members agree to follow the cooperative’s Terms and Conditions of Service, as outlined in the Code of Regulations, and to pay the rate established by the Board of Trustees.
- Before work can be performed at your location, the member/applicant must sign and return the membership application.
- If the form is not returned within 30 days, service may be scheduled for immediate disconnection.
- A $75 reconnect fee will be applied before service can be restored.
- If the form is not returned within 30 days, service may be scheduled for immediate disconnection.
To better provide valuable information to member/applicants:
- Agreement is given to receive automated informational phone messages
- Agreement is given that:
- $6.50 of the amount paid for electricity each year is allocated to a subscription for the cooperative magazine
These communication tools are used to share current and past concerns with the membership as a whole on a monthly basis.
Document Library
Before electric service is energized or re-energized:
- An electrical inspection is required by Paulding Putnam
- Documented verification of the inspection must be provided
Inspection requirements vary by location:
- In areas with a local inspection authority (AHJ):
- The local authority must be contacted
- All permitting and inspection requirements must be followed
- In areas without a local inspection authority:
- Verification must be provided that an electrician has inspected:
- The meter base
- Member-owned equipment
- Verification must be provided that an electrician has inspected:
Manufactured homes:
- Inspections must be performed by a certified electrical inspector from:
- Ohio Department of Commerce – Division of Industrial Compliance/Building Code Compliance (DIC), or
- Indiana Department of Homeland Security – Fire and Building Safety Section (IDHS)
After inspection:
- The electrician or certified inspector must complete the bottom portion of the required document
BBB List of Electricians
Inspection Form - Non-Manufactured Home
Inspection Form - Manufactured Home
Easements
An easement on your property may be required by Paulding Putnam to:
- Install power lines, poles, or underground utilities
- Maintain, repair, or upgrade electric facilities
- Grant legal access to specific portions of private property
What is the purpose of an easement?
- Allow necessary work to be performed
- Help ensure reliable power service
These easements are vital to maintaining the safety and efficiency of the electric grid and to minimizing service disruptions for all cooperative members.
Ohio Easement (PDF) Indiana Easement (PDF)
For questions or assistance:
The Paulding Putnam Engineering Department may be contacted at (800) 686-2357.
Temporary Overhead Services Installation Guide (PDF) Temporary Underground Services Installation Guide (PDF)For new homes and business applying for service from Paulding Putnam. An order must be called into Paulding Putnam Member Service at 800-686-2357.
Electrical Data Load SheetService Upgrades
If an electric service upgrade is being planned:
- A licensed electrician must sign off on any upgrades, new services, or temporary disconnects.
Depending on the application:
- A 200- or 320-amp meter base will be provided by Paulding Putnam
Meter base details:
- No charge is applied for a 200-amp meter base
- Members are responsible for the cost of any meter base larger than 200 amps
Timing and inspection requirements:
- The office must be contacted at least 60 working days before work begins (10 days for temporary disconnects)
- Service will be safely de-energized prior to the upgrade
- An electrical inspection is required before service can be re-energized
- The appropriate inspection form located below must be completed
New Construction
New homes and new construction on Paulding Putnam lines are welcomed.
Before contacting the office, the following must be completed and reviewed:
- Membership sign-up
- Required for new members only
- Must be completed online, by phone, or in the office
- Electrical Data Load Sheet
- Required for new members and loads only
- Must be completed online, by phone, or in the office
The sections below provide a complete timeline and breakdown of requests. If you want to speak with us about upgrading your service, please call (800) 686-2357 or email Member Services.
To establish service at a location without existing electric facilities, potential members will be asked to call to provide information about themselves and their potential energy needs or fill out our new service application online.
Before calling our office, please review a list of potential questions (PDF) that you will be asked about your planned construction project and your energy needs.
If you have never had service with Paulding Putnam before, you must complete a membership application. This can be done over the phone or in our office. A soft credit check will be run on the individual submitting the application.
The next step is to meet with our Staking Technician at the building site to review the service's installation options.
Before scheduling this meeting, the following must be completed:
- All buildings must be staked.
- The driveway must be marked.
- The locations of the septic/leech field and well must be approved by the governing county (and preferably staked).
During this meeting, the Technician will provide you with options and a final site plan that shows how the service should be installed, an upfront cost contribution-in-aid-of-construction quote (if applicable), a checklist for installation of your service, spec drawings, and instructions on how to proceed if any further steps need to be completed.
Please bring a copy of the deed or survey to this meeting.
If any Contribution-in-Aid-of-Construction amounts are required, they must be paid before construction of electric facilities can be scheduled. If there are additional construction responsibilities (e.g., tree trimming, final grading, conduit installation), they must also be completed before construction is planned. These additional responsibilities will be outlined in the checklist and discussed during the meeting with the staking technician.
Members are responsible for trenching and insulating approved conduit systems in underground applications. The trench and conduit must be constructed and installed to Paulding Putnam specifications as outlined on the Guideline Checklist (provided during the staking meeting), and a Paulding Putnam technician will inspect them prior to scheduling final connections.
Note: Members are also responsible for contacting 811, or visiting the call811 website, 48 hours before construction is to start.
When the member’s construction responsibilities have been completed and all electrical inspections have been secured, Paulding Putnam will schedule your job for construction accordingly.
If you have any questions, please get in touch with Paulding Putnam at (800) 686-2357.
Once all required information is received, all new electric service requests will follow a standard 60 business-day timeline. This structured process ensures fairness, transparency, and efficiency for every member request.
We’ll always work to complete projects sooner, but some factors—weather, permits, or material availability—may extend timelines. Clear expectations mean fewer delays, better communication, and more focus on completing the work.
We appreciate your patience as we continue balancing our growing electric and broadband operations while serving all members with fairness and accountability.
60-day window under normal conditions:
- Initial contact and meetings (est. 3 to 5 days): Site visit(s), review of load requirements, project intent, and initial member/developer coordination.
- Engineering review & system impact study (est. 5 to 10 days): Includes voltage drop studies, capacity checks, and review of any upgrades or special considerations.
- Field staking and physical design (est. 5 to 10 days): Staking Technicians visit the site and mark out the proposed design for construction.
- Permitting, easements, billing, and inspection prep (est. 10 to 15 days): Coordination with local authorities, property owners, and internal teams to file required documents.
- Material procurement (est. 10 to 15 days): If needed materials are not currently in inventory, this timeframe includes sourcing and receiving them—subject to vendor availability and lead times. Any significant delays due to material shortages will extend the 60-day window, and we’ll communicate that clearly when it happens.
- Processing of aid-to-construction payments (est. 3 to 5 days): Payments must be received, verified, and recorded before scheduling can begin.
- Utility locates and pre-construction (est. 5 to 10 days): 811 locates must be called in and honored before construction can proceed.
- Scheduling construction and coordination (est. 10 to 15 days): Jobs are slotted based on crew or contractor availability, and any required specialty work (boring, metering, etc.) is coordinated here.
We will always strive to complete work ahead of schedule when possible. Likewise, there may be times when external factors, such as weather, vendor delays, permit hold-ups, or complex engineering needs, may cause projects to take longer than 60 days. If you have any questions or concerns, please get in touch with our office at (800) 686-2357 or email Member Services.